FILE: FGA

SUPERVISION OF CONSTRUCTION

The School Board shall require from the Superintendent or the designated construction supervisor, a review of the architect's activities in his administration of building construction. The Superintendent shall make periodic reports certifying by his personal knowledge that the work of the construction contractor and the architect is being performed in accordance with plans, specifications, and contracts.

Requests made by contractors for extensions of time to their contracts, for delay or days missed due to inclement weather, shall be documented on a day by day basis and submitted for the Board's consideration. No extension shall be granted where proper documentation has not been submitted and the penalty clause of the contract shall be enforced.

Upon completion of the building construction and a final inspection of all its aspects by the architect, contractors, and school officials, a recommendation for its acceptance may be made to the Board.

Ref: La. Rev. Stat. Ann. §17:81.